Casting of ground floor slab and work on the first floor.

I'm updating the progress on site since the last blog. The ground floor slab has been cast, the centering for the 2nd slab is about to start and the walls and columns on the 1st floor are being done. I'm putting up some of the snaps from site during this sequence.
Centering for the ground floor roof in progress.




Form work for the roof complete.

The slab after being cast and the new columns for the first floor being raised and the centering being removed on the ground level.

The block work for the first floor in progress.